The Welcome Home Project is a campaign to renew our church family home at the Orchard Campus, in order to renew our shared mission in this community for the long-term.
By God’s grace, we hope to construct a new Kids Ministry Wing as well as a new multi-purpose Gymnasium. The lobby will be renovated and the offices and meeting rooms will move to the old Kids area.
The Welcome Home Project is seeking to address 4 key priorities:
CLICK HERE TO RE-AFFIRM, REVISE, OR MAKE A FIRST-TIME PLEDGE
Floor Plans
Timelines
- Zoning Bylaw Amendment was approved in December 2023.
- The new septic system received approval from the Ministry of Environment in February 2024.
- We have applied for a Site Plan Amendment, and expect that approval shortly. We are waiting on a clearance letter from government on our archaeological study conducted in Summer 2023.
- Our architect (Brouwer Architecture) has applied for Building Permits.
- Our construction manager (Duomax Construction) has tendered bids from trades in late May 2024.
- Construction is scheduled to begin in late August, with 12-14 month timeline to completion.
Financial Information
Our construction budget of $7,100,000 includes a contingency of $300,000. We are projecting the following funding sources:
Capital Development Fund Balance: $2,800,000
Town Campus Severance Sale (closed May 31): $1,850,000
Pledges Made in 2022 Yet to be Given: $1,175,000
Interest Earned By Capital Development Fund: $110,000
Projected Mortgage: $1,165,000